Scheduling - Nomination and Confirmation Timeline (MCT)
Scheduling Cycles |
Current Timelines |
Timely |
Nomination Deadline |
12:00 PM |
Confirmation Deadline |
3:30 PM |
Scheduled Quantity |
4:00 PM |
Start of Gas Flow |
8:00 AM |
|
|
Evening |
Nomination Deadline |
5:00 PM |
Confirmation |
8:00 PM |
Scheduled Issued |
9:00 PM |
Start of Gas Flow |
8:00 AM |
IT Bump Rights |
bumpable |
|
|
Intraday 1 |
Nomination Deadline |
9:00 AM |
Confirmation |
11:30 AM |
Scheduled Issued |
12:00 PM |
Start of Gas Flow |
1:00 PM |
IT Bump Rights |
bumpable |
|
|
Intraday 2 |
Nomination Deadline |
1:30 PM |
Confirmation |
4:00 PM |
Scheduled Issued |
4:30 PM |
Start of Gas Flow |
5:00 PM |
IT Bump Rights |
bumpable |
|
|
Intraday 3 |
Nomination Deadline |
6:00 PM |
Confirmation |
8:30 PM |
Scheduled Issued |
9:00 PM |
Start of Gas Flow |
9:00 PM |
IT Bump Rights |
no bump |
|
|
Process |
Current Timelines (as of April 1, 2016) |
Offer Tendered/Bidding Start |
8:00 AM |
Open Seasons/Bidding End |
9:00 AM |
Award for non-match bids |
10:00 AM |
Match Communicated |
10:00 AM |
Match Response |
10:30 AM |
Award for match bids |
11:00 AM |
|
Cycle |
Current Timelines (as of April 1, 2016) |
Timely |
11:00 AM |
Evening |
4:00 PM |
Intraday 1 |
8:00 AM |
Intraday 2 |
12:30 PM |
Intraday 3 |
5:00 PM |
|
Cycle |
Current Notification (as of April 1, 2016) |
Timely |
7:00 AM |
Early Evening |
2:00 PM |
Evening |
4:00 PM |
Intraday 1 |
6:00 AM |
Intraday 2 |
1:30 PM |
Intraday 3 |
N/A |
|