Maintenance Construction Schedule - MountainWest Pipeline



2025 Schedule

Period Category Preliminary Dates Duration Location Project Possible Customer Impact Current Capacity (Dth/d) Restricted Capacity (Dth/d) Anticipated Firm Cut Quantity Anticipated Total Nomination Cut %
April Reservoir Testing April 1 - 10 9 Days Clay Basin Annual Withdrawal Test No physical injections allowed starting GD March 29 through GD March 31.
•GD April 1, constant 250 MMcf/day WD rate.
•GD April 2, constant 275 MMcf/day WD rate.
•GD April 3 through GD April 9, reservoir shut-in
Varies, see latest EBB posting April 1 258,000 Dth/d, April 2 284,000 Dth/d, April 3-9 to 0. All 100%
April Compressor Maintenance April 1 - 3 3 Days Simon Compressor Station Annual Emergency Shutdown (ESD) and Unit Maintenance Capacity reduction on ML22 to Nightingale Segment of 27,650 Dth/d. Increased ML22 pressures for Vermillion Plant MAP 293, Skull Creek Delivery MAP 167, Skull Creek Receipt MAP 967 Cycle 1 GD 4/1 through Cycle 4 GD 4/3. Nominations return to normal beginning Cycle 5 GD 4/3. Nightingale ML22 Segment 206,650 Dth/d Nightingale ML 22 179,000 Dth/d 0 Dth 13%
April Compressor Maintenance April 15 - 17 3 Days Oak Spring Compressor Station Annual Emergency Shutdown (ESD) and Unit Maintenance Capacity reduction of 120,000 Dth/d ML 104 Goshen Segment Beginning Cycle 1 GD 4/15 through Cycle 5 GD 4/17. Nominations return to normal beginning Cycle 1 GD 4/18. ML 104 Goshen 384,500 Dth/d ML 104 Goshen 264,500 Dth/d TBD 31%
May - July Compressor Maintenance May 7 - July 25 79 Days Leroy Compressor Station Engine Exchange Capacity Reduction on MAP 89 Aquifer Injection of 30,000 Dth/d beginning Cycle 1 GD May 7 through Cycle 3 GD July 25. Nominations return to normal beginning Cycle 4 GD July 25. Aquifer Storage INJ MAP 898 61,200 Dth/d Aquifer Storage INJ MAP 898 31,200 Dth/d 30,000 Dth 49%
May Compressor Maintenance May 14 1 Day Kanda Compressor Station Annual Emergency Shutdown (ESD) and Unit Maintenance Kanda/Col CIG DEL MAP 171, Kanda/Col CIG REC MAP 871 no flow beginning Cycle 1 GD 5/14 through Cycle 4 GD 5/14. Nominations return to normal beginning Cycle 5 GD 5/14. Kanda/Col CIG DEL MAP 171 178,000 Dth/d. Kanda/Col CIG REC MAP 871 138,000 Dth/d Kanda/Col CIG DEL MAP 171 and Kanda/Col CIG REC MAP 871 to 0 All 100%
May Compressor Maintenance May 20 - 23 4 Days Thistle Creek Compressor Station Engine Exchange Capacity reduction of 82,500 Dth/d ML 104 Goshen Segment beginning Cycle 1 GD 5/20 through Cycle 5 GD 5/23. Nominations return to normal Cycle 1 GD 5/24 ML 104 Goshen 384,500 Dth/d ML 104 Goshen 302,000 Dth/d TBD 21%
July Compressor Maintenance July 8 - 11 4 Days Simon Compressor Station Engine Exchange Capacity reduction on ML22 to Nightingale Segment of 27,650 Dth/d. Increased ML22 pressures for Vermillion Plant MAP 293, Skull Creek Delivery MAP 167, Skull Creek Receipt MAP 967 Cycle 1 GD 7/8 through Cycle 5 GD 7/11. Nominations return to normal beginning Cycle 1 GD 7/12. Nightingale ML22 Segment 206,650 Dth/d Nightingale ML 22 179,000 Dth/d TBD 13%
October Reservoir Test October 1 - 10 9 Days Clay Basin Annual Injection Test No physical withdraws allowed from GD September 27 through GD September 29.
•GD September 30, constant 225 MMcf/day INJ rate.
•GD October 1, constant 250 MMcf/day INJ rate.
•GD October 2 through GD October 8, reservoir shut-in
Varies, see latest EBB posting September 30 Dth TBD, October 1 Dth TBD, October 2-9 to 0. All 100%

Note: This schedule is subject to change. It is recommended the Shippers monitor MountainWest Pipeline's critical notices about schedule revisions.