Notice Type Desc | Post Date/Time | Notice Eff Date/Time | Notice ID | Subject | Rsp Date/Time | Notice Stat | Prior Notice | Reqrd Rsp |
---|---|---|---|---|---|---|---|---|
STORAGE/OFO/PLND OUTAGE | 08/28/2024 10:30 AM | 09/03/2024 09:00 AM | 35083 | 2024 CLAY BASIN INJECTION TEST | 1 | 5 |
MountainWest Pipeline, LLC (MWP) has issued an update for the planned Injection Test at Clay Basin Storage. Please review all entries for upcoming work here: MountainWest Pipeline (MWP): Construction and Maintenance Schedule (mwpipe.com).
MWP scheduled the annual Clay Basin Injection test for gas days October 1 – October 9, 2024. Listed below is a schedule for this year’s test. All references are to gas days:
September 3: MWP will issue Operational Flow Orders to all FSS customers indicating their required injection volumes.
September 28 – September 30: Field limited to physical injection only. No withdrawal nominations will be accepted.
October 1: The reservoir will be conditioned at a constant injection rate of 200 MMcf (209 Mdth) for 24 hours.
October 2: Reservoir test at a constant injection rate of 225 MMcf (235 Mdth) for 24 hours.
October 3 – October 9: Field shut in. Only in-place transfer nominations will be processed.
October 10: Field returns to normal at 8:00 AM.
If you have any questions, please contact your MWP Marketing or Contract Services Representative or Scheduling on the Customer Service Hotline at 801-584-6034.