Notice Type Desc | Post Date/Time | Notice Eff Date/Time | Notice ID | Subject | Rsp Date/Time | Notice Stat | Prior Notice | Reqrd Rsp |
---|---|---|---|---|---|---|---|---|
CONSTRAINT | 07/18/2024 12:03 PM | 08/25/2024 09:00 AM | 34844 | CRITICAL, CONSTRAINT, 20240718, MOUNTAINWEST, 092027077 -->DEVIL'S PLAYGROUND CONSTRUCTION ML 103 | 1 | 5 |
MountainWest Pipeline, LLC (MWP) is issuing this notice to inform of a date change to the Devil’s Playground Project construction dates. The original outage dates for construction were August 5 – August 9 and have been moved to August 25 – August 30.
No nominations will be allowed on the ML 103 Fidlar segment beginning Gas Day August 25, 2024, Timely Cycle and extending through Gas Day August 30, 2024, ID3 Cycle. Nominations will be allowed to return for Gas Day August 31, 2024, Timely Cycle.
If you have any questions, please contact your MWP Marketing or Contract Services Representative or Scheduling on the Customer Service Hotline at 801-584-6034.